| This Guide is intended to aid in the proper
design, specification, and installation of brick paving systems.
The designs presented in this Guide are not intended as a
replacement to the advice of an experienced pavement designer.
Although the proposed pavement sections may be appropriate
in developing preliminary sections and budget costs, it is
recommended that an engineer with appropriate pavement experience
certify the final design.
Click on images for larger view.
General
[top]
Flexible brick pavements, as defined in this
Guide, consist of sand set or bituminous set brick pavers
over layers of conventional pavement materials. The flexible
brick pavement shown in Figure 1 consists of a compacted subgrade
beneath a subbase layer, base layer, and setting bed surfaced
with brick pavers and jointing sand. A subbase may not always
be necessary between the subgrade and the base. An edge restraint
is provided around the flexible brick pavement as part of
the system. Sand set brick pavers, and to a lesser extent
bituminous set brick pavers, with sand filled joints, develop
interlock between adjacent pavers, which distributes the applied
loads into the underlying layers. This does not occur with
mortar set pavers. Mortared brick paving is only used over
a concrete slab and is not covered in this Guide. Although
this pavement type has been used successfully, the emphasis
in this Guide is on flexible wearing surfaces. Information
on other types of brick pavements can be found in BIAA Technical
Notes on BrickConstruction 14 Series.
Interlock is a phenomenon that occurs in segmental
pavements as a result of the interaction of the pavers and
the jointing sand between the pavers. The tight, sand-filled
joints transfer loads between adjacent brick pavers through
friction. Interlock increases over time as the joint sand
becomes thoroughly compacted and debris builds up in the joints.
When interlock is present, the wearing surface contributes
to the strength of the system. Specially-shaped pavers provide
little additional contribution to vertical interlock. However,
some bond patterns, such as herringbone, help to distribute
horizontal loads. In areas subjected to heavy vehicular traffic,
the brick pavers may be required to have a minimum thickness
to achieve sufficient interlock.
 |
Figure 1. Flexible
Brick Pavement |
Adequate design and construction results in three
types of interlock: vertical interlock, rotational interlock,
and horizontal interlock. See Figure 2. If a vertical load
were applied to a single brick in a pavement without vertical
interlock, that brick would be forced down between adjacent
bricks, transmitting concentrated stresses onto the setting
bed. Brick pavers that are compacted into the setting bed
and have well consolidated sand in the joints between them
provide shear resistance in the wearing surface. Thus, the
load is spread over a wide area of setting bed. See Figure
2. Sand set pavers develop greater vertical interlock than
bituminous set pavers as they are vibrated to compact the
sand bed and densify the joint sand to a higher degree.
|
Figure 2. Vertical
Interlock |
If a load is applied asymmetrically to an individual
brick, the brick may rotate, displacing the setting bed and
adjacent bricks. Rotational interlock holds the brick in place
while rigid edge restraints prevent the bricks from moving
laterally, thereby eliminating rotation. See Figure 3.
|
Figure 3. Rotational
Interlock |
|
Figure 4. Horizontal
Interlock |
Horizontal interlock is not achieved if horizontal
movement is allowed. In vehicular traffic areas, horizontal
braking, cornering and accelerating forces try to move pavers
along the road; this is known as creep. Sand filled joints
and an interlocking bond pattern transfer these forces within
a paving area to rigid edging. See Figure 4. Loads created
by turning vehicular traffic are distributed more evenly in
all directions by a herringbone pattern than by running bond
pattern, which has acceptable horizontal interlock in only
one direction. See Figure 5. Basket weave patterns may have
continuous joints in two directions, resulting in unacceptable
horizontal interlock. Sand set brick pavers initially develop
greater horizontal interlock than bituminous set brick pavers
as the joint sand is better compacted.
|
Figure 5. Horizontal
Load Interlock |
Although a flexible brick pavement provides a
durable surface for light or heavy vehicular applications,
the surface of a segmental pavement may not provide a smooth
ride at high speeds. Brick roads tend to slow traffic as subtle
variations in the surface cause decreasing ride comfort as
speed increases. These variations help reduce speeds in areas
where faster vehicular traffic may be a concern. This is one
of many traffic calming measures that cities use to slow traffic
in residential neighborhoods. However, segmental pavements
are not recommended where vehicle speeds exceed 40 mph (64
kph).
Deciding on the appropriate brick paving system
to use is important to ensure proper performance. Since brick
can be used in a variety of ways, as shown in Figure
6, Table 1 is provided to assist in selecting the most
appropriate system.
|
Figure 6. Brick
Paving Systems |
Part
1: Structural Design and Detailing [top]
Introduction The
AASHTO methodology was described in detail in the first edition
of this Guide. Direction was given on determining the amount
of traffic that would use the pavement, dependent on the many
factors identified in the 1993 AASHTO Design Guide. Tables
were provided for calculating the estimated traffic in the
design lane based upon axle loads, equivalency factors, structural
numbers, growth factors and lane distribution factors. The
equations used to calculate the required structural number
for the pavement, and to proportion the individual pavement
layers were set out, along with figures and tables to assess
the layer and drainage coefficients necessary to design the
pavement. In addition, nomographs and design examples were
provided to clarify the procedure.
This version of the Guide provides a method based
upon specific applications and site conditions rather than
the more complex procedure of the first edition. The design
solutions were prepared in accordance with the AASHTO methodology,
and the input values are declared in the relevant sections.
Although the proposed pavement sections may be appropriate
in developing preliminary sections and budget costs, it is
recommended that the final design be certified by an engineer
with pavement design experience.
In addition to these revisions related to the
AASHTO design method, this edition also discusses an alternative
design method for use in those states that have adopted the
Caltrans design method or derivations thereof. Design solutions
are not provided using this method, but gravel equivalent
factors are suggested for use with the Caltrans manual, so
that it can be adapted to consider brick pavers.
Because of the range of climates and the variability
of soils, base and subbase materials, designers must use good
engineering judgment in detailing a flexible brick paving
system. The designer should be acquainted with site conditions
and use all available resources to create a cost-effective
solution. Consult references listed at the end of this Guide
for more information.
Table 1 Brick Paving System Selection
[top]
| System |
Advantages |
Disadvantages |
Flexible brick paving
over flexible base (Fig. 6a) |
Most durable over time
Easy to repair utilities
Usually most economical
Allows use of semi-skilled labor
|
May require a thicker base
Permits some water percolation through system
|
Flexible brick paving over semi-rigid
base
(Fig. 6b) |
Good as an overlay to existing pavement
Good over poor soils or small, confined areas
Better aesthetic repairs than continuous concrete |
Requires good drainage
More expensive
Vulnerable to frost heave |
| Setting sand system |
Good load transfer
Simple and expedient installation
Pavers easily reused for repairs |
Susceptible to deficiencies in the bedding sand
Susceptible to sand loss and creep issues |
| Bituminous setting system |
Enhanced water resistance
Good containment of setting bed material
Less onerous edge restraint requirements |
More expensive and slower to install
Pavers difficult to salvage during repair work
Poor tolerance to paver thickness variations or poor
base elevations |
Mortared paving over rigid base
(Fig. 6d) |
Matches adjacent walls with mortar joints
Good over poor soils
Can be used on steeper grades |
Must have a concrete base
Most costly of all brick paving
Requires maintenance of mortar joints
Requires movement joints |
Subgrade
Classification [top]
The subgrade is classified by the existing soil
conditions, the environment and drainage. The more accurate
the subgrade classification, the better the performance of
the pavement.
Table 2 Subgrade Categories [top]
| Subgrade Category |
CBR Range |
R-value Range |
| Unsuitable |
< 2.9 |
< 6 |
| Poor |
3.0 - 5.9 |
6 - 13 |
| Fair |
6.0 - 9.9 |
14 - 24 |
| Good |
10.0 - 14.9 |
25 - 38 |
| Excellent |
> 15.0 |
>38 |
Table 3 Subgrade Categories from USCS
USCS
Designation |
Environmental/Drainage
Conditions |
| Wet |
Average |
Dry |
Frost |
| GW |
E |
E |
E |
E |
| GP |
E |
E |
E |
E |
| GW-GM |
E |
E |
E |
G |
| GW-GC |
E |
E |
E |
G |
| GP-GM |
E |
E |
E |
G |
| GP-GC |
E |
E |
E |
G |
| GM |
E |
E |
E |
P |
| GC` |
E |
E |
E |
P |
| GM-GC |
E |
E |
E |
P |
| SW |
E |
E |
E |
E |
| SP |
G |
E |
E |
E |
| SW-SM |
G |
E |
E |
F |
| SW-SC |
G |
E |
E |
F |
| SP-SM |
G |
E |
E |
F |
| SP-SC |
F |
G |
E |
F |
| SM |
G |
E |
E |
U |
| SC |
F |
G |
E |
P |
| SC-SM |
G |
E |
E |
U |
| CL |
P |
F |
G |
P |
| CL-ML |
P |
F |
G |
U |
| ML |
P |
F |
G |
U |
| OL |
U |
U |
U |
U |
| CH |
P |
P |
F |
P |
| MH |
P |
F |
F |
U |
| OH |
U |
U |
U |
U |
Soil Conditions
The
existing soil conditions for a project should be determined
prior to commencing the design of the pavement sections. A
geotechnical engineer who specializes in site investigation
work will generally test and classify the soil conditions
for the project area. Testing will be carried out at the project
site and samples will be recovered for additional testing
in the laboratory.
The site investigation should include test pits
and borings along the alignment of the road or street, or
over the area of the pavement. Samples should be collected
for the following laboratory tests considered essential to
determine the engineering properties of the soils over which
the pavement will be constructed:
- Grain-size distribution: sieve analysis test
and hydrometer test to determine the percentage of the individual
grain sizes in the sample;
- Atterberg Limits: consistency tests to determine
the moisture content at which the sample changes from a
semi-solid state to a plastic state (Plastic Limit) and
from a plastic state to a liquid state (Liquid Limit);
- Natural moisture content: test to determine
the in-place moisture content of the soil;
- Natural Density: test to determine the in-place
density of the soil;
- Dry density/optimum moisture content relationship
(standard or modified): compaction test to determine the
ideal moisture content to achieve the specified state of
compaction;
- Strength tests [California Bearing Ratio (CBR)
or Resistance Value (R-value)]: mechanical tests to determine
the bearing capacity of the soil for use in the design.
The CBR test method is set out in ASTM D 1883
Test Method for CBR of Laboratory Compacted Soils (AASHTO
T193). It can be conducted on treated and untreated base,
subbase and subgrade materials. This test is a comparative
measure of the load-bearing capacity of a soil. It measures
the load required to drive a standard plunger a set depth
into a sample of soil at a standard rate of penetration. The
CBR value is the ratio of the load measured in the test and
the load used to achieve the same penetration in a standard
sample of crushed stone. The test is generally undertaken
in the laboratory, but in-place tests can also be carried
out. The values are greatly affected by the degree of compaction
and the moisture content of the specimen. The test should
be conducted on a specimen compacted to a density representative
of the material to be used in the pavement, or alternatively
at a range of densities likely to be encountered. To represent
the materialÕs potential moisture condition in the pavement,
the test should be conducted on specimens that have been soaked
after compaction for a period of four days.
The R-value test method is set out in ASTM D
2844 Test Method for Resistance R-Value and Expansion Pressure
of Compacted Soils (AASHTO T190). It can be conducted on treated
and untreated base, subbase and subgrade materials, but the
test can only be undertaken in the laboratory. For base, subbase
and non-expansive granular soils, the R-value is determined
at a density equivalent to the density used during construction.
For cohesive soils and expansive granular materials, the R-value
test involves two separate procedures. One procedure calculates
the estimated thickness of the overlying pavement layers required
to maintain the state of compaction of the material. The other
procedure estimates the thickness of the overlying pavement
layers required to prevent plastic deformation in the material.
The R-value is determined at the moisture content and density
at which the thickness of overlying materials is similar in
the two procedures.
The AASHTO design method uses the resilient modulus
(MR) as the design input for the subgrade properties. The
mean value of all test results for each pavement section or
soil type should be used for design. The test to directly
determine MR is not widely used, so AASHTO has proposed the
following relationships between the CBR and R-value test results.
These relationships are as follows:
MR (MPa) = 10.3 X CBR (Eq.
1)
Where: MR is the resilient modulus and CBR is the California
Bearing Ratio
MR (MPa) = 6.9 + 3.8 X R-value (Eq.
2)
The Caltrans design method uses the R-value as
the design input for the subgrade properties. The lowest R-value
should be used for design over a section of pavement. However,
if there are one or two significantly lower R-values in a
localized section, consideration should be given to replacing
these areas with better material and using the next lowest
value.
Soils or subgrades are typically classified into
different groups to represent their engineering properties.
There are several systems used in the United States, but the
two most common are the Unified Soil Classification System
(USCS), used for general engineering purposes, and the AASHTO
System, used for highway engineering purposes. The USCS is
set out in ASTM D 2487 and the AASHTO system is set out in
AASHTO Standard M145, Classification of Soils and Soil-Aggregate
Mixtures for Highway Construction.
In the USCS, the soils are classified in twenty-five
groups by two letter designations dependent on the soil type
and physical properties. The first letter represents the main
soil type (gravel, sand, silt, clay or organic), and the second
modifies the first letter based upon the grain-size distribution
for granular soils or the Atterberg Limits for cohesive soils.
Eleven groups have paired designations. In the AASHTO system,
the soils are classified in seven main groups (and in twelve
sub-groups) based upon their grain-size distribution and Atterberg
Limits. The two systems are given in Tables 3 and 4, in a
manner that correlates each group with the suggested subgrade
categories (U -unsatisfactory, P - poor, F - fair, G - good,
E - excellent).
A geotechnical engineer’s report will include
a description of the soils encountered at the project site
and will set out the test results. In addition, it will generally
provide recommendations on the strength properties of the
soils to be used for design and may contain some design options
for the pavement section. If a recommended value is given
in the report, this should be used to select the subgrade
category (see Table 2). If there is no recommended value,
but CBR or R-value test results are given, the average of
these values should be used for the AASHTO design methodology.
When the design is to be undertaken using the Caltrans adaptation,
the minimum R-value should be used for selecting the subgrade
category. If only the subgrade’s USCS or AASHTO classification
is known, Table 3 or 4 can be used to estimate the subgrade
category from the column titled “Average”. The
remaining columns are addressed in the following section.
Environment and
Drainage [top]
Environmental conditions and the quality of subgrade
drainage can have a major effect on the support offered by
the subgrade. In wet climates, poorly drained areas, or those
that experience freezing conditions, the subgrade support
is likely to be reduced during certain periods of the pavement's
life. Conversely, in arid climates or well-drained areas,
it is likely that a higher degree of subgrade support will
be experienced during part of the pavement's life. These factors
can have a significant effect on the performance of the pavement.
Saturation of the subgrade, and the materials
in the pavement section, can lead to premature distress as
this condition reduces the strength of these materials. Water
can enter the pavement through the joints between bricks,
through cracks and joints in the bound base materials, or
from a high ground water condition. The amount of water penetrating
from the surface depends on the regional climate. Fluctuations
in moisture content can also be problematic, leading to changes
in volume and load support. Rapid removal of water from the
pavement is therefore an important design objective, and a
positive drainage system should be considered. Design of such
a system is beyond the scope of this Guide.
Table 4: Subgrade Categories from AASHTO
AASHTO
Designation |
Environmental/Drainage
Conditions |
| Wet |
Average |
Dry |
Frost |
| A-1-a |
E |
E |
E |
E |
| A-1-b |
E |
E |
E |
E |
| A-2-4 |
E |
E |
E |
G |
| A-2-5 |
E |
E |
E |
G |
| A-2-6 |
E |
E |
E |
G |
| A-2-7 |
E |
E |
E |
G |
| A-3 |
E |
E |
E |
P |
| A-4 |
E |
E |
E |
P |
| A-5 |
E |
E |
E |
P |
| A-6 |
E |
E |
E |
E |
| A-7-5 |
G |
E |
E |
E |
| A-7-6 |
G |
E |
E |
F |
Figure 7 presents the six climatic regions experienced
in the United States. It depicts two regions of hard freezes
where spring thaw conditions are likely to affect the subgrade,
two regions where there is a potential effect from frost,
but only if the pavement is thin, and two regions not susceptible
to frost. Average depths of frost penetration are indicated
for the eastern and central states, although frost depths
can vary locally based on many factors. Local data should
be used in its place if this is available for a specific project
site. This is particularly true in the western states, and
no frost depth data is therefore included in Figure 7 for
this part of the country. If the depth of frost penetration
is greater than the pavement thickness determined in this
Guide based on one of the first three columns of Tables 3
and 4, it will be necessary to revise the pavement construction.
Either non-frost susceptible material should be added to the
thickness of the pavement section so that it is thicker than
the depth of penetration, or a revised depth should be determined
based upon the anticipated loss of strength in the subgrade.
In this case, if the project is located in Regions III or
VI on Figure 7, it will be necessary to use the subgrade category
from the column for Frost Environmental/ Drainage Conditions.
If the project is located in Regions II or V, and the project
site drains poorly, it will also be necessary to use the Frost
Environmental/ Drainage Conditions column to determine the
subgrade category, since, once again, pavement thickness is
a factor.
The AASHTO design method utilizes an effective
resilient modulus that is derived from the seasonal resilient
moduli. These vary depending on the moisture conditions of
the subgrade during each season. Such an analysis is beyond
the scope of this Guide. It is recommended that the design
be undertaken using a subgrade category as described earlier
or from the geotechnical report, as the geotechnical consultants
will consider these factors when providing their recommendations.
If these values are not available, but the USCS or AASHTO
designation is known, Tables 3 and 4 should be used to develop
the appropriate subgrade category. Most pavements should be
designed using the subgrade category from the column for Average
Environmental/Drainage Conditions. However, if the project
is located in Regions I, II or III of Figure 7, and the project
site drains poorly, such that the subgrade is frequently saturated,
it will be necessary to use the subgrade category from the
column for Wet Environmental/Drainage Conditions. If the project
is located in Regions IV, V or VI and the project site drains
well, such that the subgrade is rarely saturated, it may be
appropriate to use the column for Dry Environmental/ Drainage
Conditions.
Traffic
Analysis [top]
The traffic analysis for the project should be
undertaken before commencing design of the pavement sections.
A traffic engineer is typically contracted for this work.
When undertaking a design it is necessary to determine the
existing (or initial) traffic volume using the road, and to
estimate the future traffic volumes over the analysis period.
Based upon these data and local experience, it is necessary
to establish the traffic flow in each direction and in the
design lane. Most of the damage to a pavement is caused by
truck traffic; passenger cars, pick-ups and light two axle
trucks generally have a negligible effect. Using local data
on the anticipated types of vehicles that will use the road,
the number of load applications of each axle group can be
calculated. Next, all of the repetitions of each axle group
are converted into the equivalent number of repetitions of
one axle load condition.

In the AASHTO design methodology, the traffic
is represented as the equivalent number of load applications
of an 18-kip axle load that represents the mixed traffic using
the pavement. This is known as an equivalent single axle load
(ESAL). Tables in the AASHTO Design Guide provide values for
converting different axle loads into ESALs.
In the Caltrans method, this number of ESALs
is further converted into a traffic index (TI). This varies
in accordance with Equation 3 below, except that the TI is
rounded to the nearest 0.5:
TI = 9.0 X (ESAL/106)0.119 (Eq.
3)
In this Guide, a simplified approach is adopted
using pavement classes. Nine pavement classes are identified
in Table 5, together with a description of their anticipated
use and an indication of the total number of ESALs and TI
for each class.
The life of the pavement can be expressed in
a number of ways depending on local policy. Two terms are
used in the AASHTO Design Guide covering different long-term
strategies. These are the performance period and the analysis
period. The performance period is the length of time that
a pavement will remain serviceable before it requires rehabilitation
such as an overlay. The analysis period is the amount of time
over which the pavement life is to be considered, including
any rehabilitation work. For high volume roads (collectors
and above), an analysis period of at least thirty years is
frequently considered. For low volume roads (locals and below)
and all other pavements, a twenty-year life is generally acceptable.
As rehabilitation of flexible brick pavements cannot be achieved
by strengthening measures without lifting the bricks, this
Guide considers the analysis period as the design life of
the pavement.

AASHTO Design Concepts
[top]
The AASHTO Design Guide is based upon empirical
test results from full-scale road tests conducted in the 1960’s.
As a result of the measured behavior of the test sections,
the researchers developed a performance equation upon which
design of new pavement sections can be achieved. The equation
relates the design life, in terms of 18 kip ESALs, to a number
of different input parameters. These include the reliability
of the pavement, the acceptable level of loss in serviceability,
the variability of the traffic predictions and performance,
the structural number and the average subgrade resilient modulus.
The reliability of the designed pavement section
is an important feature in the AASHTO design process. The
reliability of the pavement is the probability that it will
perform satisfactorily over its design life for the traffic
and environmental conditions experienced. The reliability
level adopted in this Guide is taken as an 85 percent likelihood
that the pavement will reach its design life (analysis period)
for pavements with high traffic volumes (collectors and above);
and a 75 percent likelihood that the pavement will reach its
intended design life for pavements with low traffic volumes
(locals and below). Non-highway pavements are also considered
to have a reliability of 75 percent. This means that 85 percent
or 75 percent of the pavements for each respective use would
achieve or exceed the design life.
The AASHTO design method uses a subjective measure
of the loss of serviceability and failure of the pavement.
It was developed as an interpretation of the quality of the
ride experienced by the average road user. A scale from 0
to 5 represents the quality of the ride and is known as the
Present Serviceability Index (PSI). A PSI of 0 represents
an impassable road while a PSI of 5 represents a perfect road.
The change between the initial and final (terminal) PSI, known
as the Serviceability Loss, used in this Guide is taken as
1.7 for high traffic volumes and 2.2 for low traffic volumes.
This is based upon an initial value of 4.2 and terminal values
of 2.5 and 2.0 respectively. This compares favorably with
those used for typical flexible pavements. An exception is
in pedestrian areas where the potential for trip hazards is
an important consideration. Therefore, a serviceability loss
of 1.7 is recommended in these locations. Other AASHTO reliability
parameters are presented in Table 6.
The variability of the traffic prediction and
pavement performance is taken as 0.35. This is comparable
with the figures used for flexible pavements using asphaltic
concrete as a surface course.
The structural number is the only parameter directly related
to the pavement section. It is derived from the layer coefficient
of each layer, the thickness of each layer, and the drainage
coefficient for each layer. This Guide is produced under the
assumption that adequate drainage will be provided to the
pavement materials such that the latter coefficient can be
taken as 1.0. Typical layer coefficients are presented in
Table 7, with the default values used in subsequent design
tables in this Guide.
The values presented in Table 7 can be used to
adjust the layer thicknesses derived from the design tables.
The ratio of the layer coefficients can be used to determine
the equivalent thickness of an alternative material. For example,
to include a 6-in. (150 mm) thick lime stabilized subbase
it is possible to reduce the aggregate base by 0.11/0.14 times
the 6-in. (150 mm) thickness, i.e. by 4.5 in. (114 mm). Similarly,
to replace 8.5 in. (216 mm) of graded crushed aggregate (CBR
100) with graded aggregate (CBR 60) multiply 8.5 by 0.14/0.12,
i.e. replace with 10 in. (254 mm) of graded aggregate. However,
it is recommended that the top of the aggregate base directly
under the paver setting bed always be constructed with graded,
crushed material that is 4 in. (100 mm) thick when the ESALs
are below 500,000 or 6 in. (150 mm) thick when the ESALs are
at 500,000 and above respectively.
AASHTO
Design Solutions [top]
Tables 8 through 11 of this Guide have been prepared
to provide design solutions to each pavement class and subgrade
category. The wearing surface is always a 2-5/8 in. (67 mm)
paver on a 1 in. (25 mm) setting bed. The bituminous setting
bed is usually specified at 3/4 in. in thickness, and an adjustment
to the developed thicknesses is required as discussed in the
bituminous setting bed section. The base is as indicated in
the tables.
Table 8 presents the thickness of graded aggregate
subbase course required for each application. The resultant
pavement section will be comprised of 2-5/8 in. (67 mm) thick
flexible brick surface on 1 in. (25 mm) of bedding sand, over
4 in. (100 mm) of crushed, graded aggregate base on top of
the thickness of graded aggregate subbase determined from
the table. Note that the thickness of crushed, graded aggregate
base is increased from 4 in. to 6 in. (100 to 150 mm) for
traffic levels over 500,000 ESALs. An unbound base course
is not considered appropriate for traffic levels above 2,000,000
ESALs.

Similarly, Table 9 provides the required thickness
of graded aggregate subbase when a cement treated base is
used under the bedding sand. Note that in this case the thickness
of cement treated base is increased from 4 in. to 6 in. (100
to 150 mm) for traffic levels over 2,000,000 ESALs. Table
10 can be used when an asphalt treated base is provided.
Table 11 provides typical portland cement concrete
slab thicknesses, with a 4 in. (100 mm) aggregate subbase
below and a wearing surface of flexible brick paving. This
table is for guidance if the bricks are to be used over such
a substrate. Little structural benefit is provided by the
bricks in this pavement section, and care needs to be exercised
in ensuring that detailing allows for thermal and moisture
induced movement in the concrete, and for egress of moisture
penetrating the brick surface.
CALTRANS
Design Concepts [top]
The Caltrans design method is also based upon
a wide range of information including: theory, test track
studies, experimental pavement sections, observations of pavement
performance, and research on materials. Pavements are generally
designed for a twenty year life, but it is accepted that asphalt
concrete surfaced pavements will require maintenance at ten
to fifteen years if they are to achieve this life. This is
generally a surface material issue, and this Guide assumes
that the brick pavers will provide a twenty year life.
The Caltrans design method considers the various
pavement materials in terms of a gravel factor (Gf). Tables
are included in the Caltrans design manual setting out the
gravel factors for various materials dependent on the materials
properties and the TI. The gravel factor is a representation
of the relative ability of the materials to resist the effects
of traffic loading, when compared to an equivalent thickness
of gravel.

The design of the pavement section is based upon
a relationship between the R-Value (R), and the Traffic Index
(TI) to develop the Gravel Equivalent (GE) for the pavement.
The relationship is represented by Equation 4:
GE (mm) = 0.975 X (TI) X (100-R)
(Eq. 4)
The procedure is carried out from the top of
the pavement to the bottom. Treated base layers generally
have an R-value greater that 100 and so the equation is typically
applied to the highest layer in the pavement section with
an R-value less than 100. The thickness of the overlying layers
is determined. The process is then used for the underlying
layer, and so on down to the subgrade. The thickness of each
layer is calculated by dividing the GE by the appropriate
Gf. The thickness of each layer is generally rounded to the
next 0.05 ft (15 mm) increment.

To allow for deviations from the specified thickness
as a result of construction procedures the Caltrans method
uses a safety factor procedure. This involves adding 0.2 ft
(60 mm) to the GE of the asphalt concrete surface material
and subtracting 0.2 ft (60 mm) from the GE of the subbase,
or if no subbase is used, from the thickness of the base.
The thickness of the brick pavers cannot be changed, and so
this practice needs to be undertaken between the base and
the subbase, if used.

Design solutions using the Caltrans procedure
are not presented in this Guide, however, a Gf of 2.0 is proposed
for the brick paver and sand setting bed, and 1.8 is proposed
for the brick pavers on a bituminous setting bed, based upon
the above noted typical relationship with equivalency to asphalt
concrete. This value can be used when the Caltrans manual
is appropriate for the design, rather than the AASHTO methodology.

Design of Bituminous Setting Bed Systems
[top]
Bituminous setting bed systems as shown in Figure
6b can be used in most of the same applications as sand setting
bed systems. Higher speed apllications are less desirable
as the interlock between pavers is reduced. Although it has
reduced structural benefits, the system can provide better
moisture protection to the underlying layers. In addition,
the bonding action of the system enables the use of pavers
with a lower standard of dimensional tolerances where wider
joints would lead to reduced “lock-up” in a sand
set system. Joint widths of up to 1/4 inch (6mm) can be tolerated,
especially in low traffic applications. As there is no vibration
used to compact the pavers, chipping is less of a problem,
particularly with pavers that do not have chamfers or lugs.
This system may also have advantages where edge restraints
are less reliable, or where movement may be encountered. This
typically occurs where pavers are placed against steel rails
for light rail applications.
The bituminous setting bed system can be used
as an alternative to a sand setting bed system. The 1 in.
(25 mm) thick sand setting bed is replaced by a 3/4 in. (19
mm) thick asphalt coated sand mixture that is “bonded”
to the underlying pavement layer using a tack coat. The brick
pavers are bonded onto this layer with a rubberized asphalt
adhesive. The joints are filled with stabilized sand, but
no vibration is used. Consequently, “lock-up”
is not as well established and the load spreading is reduced.
The base thicknesses presented in this Guide can be used for
this system; however, the thickness of the underlying layers
needs to be increased. This can be achieved by adding an additional
1 in. (25 mm) to the thickness of the cement treated base
layer, 3/4 in. (19 mm) to the thickness of the asphalt treated
base layer, or 1-1/2 in. (38 mm) to the thickness of the graded,
crushed aggregate base. No revision is necessary for the portland
cement concrete sub-slab option.
Mortared Brick Paving [top]
The structural design of mortared brick paving
follows the design of rigid pavements. The brick pavers and
the mortar setting bed are not taken into account in the thickness
design. The design of mortared brick paving is not the aim
of this Guide. Refer to the AASHTO Design Guide or BIA Technical
Notes 14 Series.
Detailing
Surface Profile [top]
Satisfactory slopes for flexible paving must
be provided to avoid ponding water. A minimum slope of 2 percent,
(1/4 in. per foot or 1 mm per 50 mm), is suggested for all
exterior brick paving. Crowns on roads usually provide adequate
slope. A maximum slope of 10 percent is recommended for flexible
brick streets and roads, since larger slopes will cause washout
of the jointing sand and braking vehicles will increase the
creep of the pavement. Surface grades of up to 15 percent,
or even 20 percent, can be used on pavement areas subject
to slow moving traffic or pedestrians. However, joint sand
stabilization, as well as a high level of installation quality,
is desirable to reduce creep that occurs.
Drainage [top]
Drainage is one of the most important design
requirements, since improper drainage may cause failure of
the pavement, erosion of the base or subbase, possible deterioration
of the pavers, or slippery pavements. Drainage needs to be
considered at three levels in the pavement. These are at the
surface, to the setting materials and to the pavement structure
and subgrade. Surface drainage is undertaken in accordance
with standard design concepts for pavement areas. The pavement
surface should be finished 1/8 to 1/4 in. (3 to 6 mm) above
drainage gratings to allow for potential secondary compaction
of the setting bed under trafficking. Surface profiles are
covered in the previous paragraph. The bond pattern may affect
the flow rate of water over the surface of the paving, as
water tends to flow along the joint lines. Surface runoff
will increase with time as the joints become filled with debris,
however, some water will penetrate the brick surface layer.
Water that penetrates the wearing surface should
be drained away from the setting bed and base when the underlying
layers are not free-draining. This is particularly the case
when the setting bed is placed over a portland cement concrete
slab or a cement or asphalt treated base. Weep holes placed
vertically through the portland cement concrete slab may be
necessary depending on the environmental conditions. Drainage
is less of a concern with bituminous setting beds as some
water will percolate through them. It may be necessary to
provide a sub-surface drainage system. Sub-surface drainage
weeps should be provided at low points and at the edge restraints
to drain water to the pavement edge or storm drains. A perforated
pipe wrapped with an appropriate geotextile material may be
used. The geotextile is necessary to keep small particles
from washing out of the setting bed into sub-surface drains.
A drainage layer of open graded aggregate may also be used,
but requires proper planning, designing and specifications.
Design and detailing of such systems are not included in this
Guide, and the reader is directed to the references for several
manuals on this subject.
Bond Patterns [top]
Many different bond patterns exist, providing
different aesthetic effects, a few of which are shown in Figure
8. Herringbone provides the best resistance to the horizontal
forces from accelerating, braking and turning of wheels, and
should be used in areas subjected to heavy vehicular traffic.
This is required for sand setting beds and recommended for
bituminous setting beds. The pattern can be oriented at 45
degrees or 90 degrees to the direction of traffic. It is not
necessary to turn the pattern at corners and bends, as the
horizontal interlock is good in all directions.
Many of the pavements laid in the 19th and 20th
Century were laid in running bond, either directly across
the streets, or occasionally at up to 45 degrees across them.
Running bond patterns have continuous joints in one direction.
They do not transfer loads well along the continuous joints,
and so careful consideration is necessary with their use.
They require smaller joints between pavers in order to minimize
creep. Running bond pattern is not recommended for high volume
roads and streets. For low traffic volume paved areas the
traffic should run perpendicular to the direction of the continuous
joints.

Other bond patterns, such as basketweave and
stack bond, can be used in pedestrian areas. This also applies
to derivations of these patterns, such as Spanish bond. In
all of these arrangements, the patterns include continuous
joints in two perpendicular directions. For most basket weave
patterns laid in a flexible pavement the bonding ratio of
the paver is 2:1 or 3:1 (length: width) for proper alignment
of the pattern. Herringbone bond, running bond and stack bond
do not have to follow this rule, although joints will not
align with a herringbone bond using an irregular module, which
may affect installation quality. Basketweave and stack bond
patterns tend to show irregularities of the pavers and misalignment
of the bond pattern more than other bond patterns. Great care
needs to be exercised with such patterns if there is any likelihood
of in-place wheel turning.
Some pedestrian plazas and other facilities have
been installed using the brick pavers in modules that coincide
with the building grids, tree pits, or other features. Other
designs have been created in herringbone bond or bands using
different color pavers. When setting out a pattern using fixed
dimension modules or different colors, it is important to
remember that the individual bricks are not exact sizes. In
a modular pattern a consistent 1/16 in. (2 mm) under or over
sizing of the bricks, allowable in standard manufacturing
tolerances, will soon lead to a shortfall or overrun of several
inches in a grid module. This should only be overcome by cutting
the bricks to fit, as spacing the pavers with wider joints
can affect the structural integrity of the pavement. When
mixing different colors of pavers in a pattern area, it is
necessary to have an understanding of the potential for different
sizes so that the desired appearance is achieved.
Edge Restraints [top]
Edge restraints are necessary along the perimeter
of the pavement to prevent lateral movement of the pavers
and loss of the setting bed. The edge restraints should be
able to resist anticipated loads with minimal movement in
order to maintain interlock. Edge restraints can be placed
before laying the setting bed, and those incorporating concrete
should be cured before compaction of the brick pavement begins.
All edge restraints should be placed to a depth of at least
the bottom of the setting bed. Edge restraints are required
for both sand set and bituminous setting methods, although
the former requires more robust construction. It is important
that the inside face of the edge restraint is vertical so
that the pavers can be laid against it without a tapered joint
that will reduce the integrity.
Concrete Dividers and Inlays [top]
In many pavement areas, the brick pavers are
laid between concrete elements that divide the pavement into
sections. These are typically 8 to 16 in. (200 to 400 mm)
wide. The perception is frequently that this will provide
the opportunity to change the pattern orientation or that
by incorporating such fixed features it will be possible to
prevent creep of the brick pavers. In actuality, it introduces
a discontinuity into the pavement that creates a weakness
within the traffic area. Placement of small cut pieces, opening
of the joints, and settlement of the pavers often occurs at
these locations. Therefore concrete dividers are not recommended.
Changes in the pattern orientation can be formed by incorporating
a header or sailor course of bricks if a band type feature
is required, by a single sawcut joint line, or by a carefully
introduced series of staggered sawcut joints to maintain continuity.
Inlays are also frequently used where a panel
of brick pavers is incorporated as an entrance feature. Such
inlays are usually surrounded by concrete dividers, or portland
cement concrete pavement. When detailing such an inlay it
is important that the sides of the dividers are vertical so
that interlock can be generated between the bricks and the
concrete. The brick pavers should be finished approximately
1/8 in. (3 mm) high against the concrete so that there is
accommodation for secondary settlement of the setting bed
under traffic. It is also advisable to keep the cut pieces
of brick against the edge divider as large as possible, with
no pieces less than a quarter of a paver. Thin slivers are
particularly vulnerable to damage at these positions. Some
benefit can be gained by incorporating a header, sailor, or
string course adjacent to the concrete edge.
Traffic Buttons, Reflectors and Paint
Markings [top]
Traffic buttons are frequently used as lane markings
in streets and roads where snow clearance is not an issue.
These buttons and reflectors are generally secured on the
pavement surface with an epoxy adhesive. Setting onto individual
brick pavers can be detrimental to the pavement. The impact
from vehicle tires can loosen and even dislodge the bricks.
It is recommended that alternative means of lane markings
are adopted for brick pavers, or that larger, low-profile
buttons are used that fix to more than one paver. One effective
solution has been to inlay concrete pavers that have a specialized
top surface finish. As concrete pavers are typically 3-1/8
(80 mm) thick, they protrude above the pavement surface sufficiently
to create tire feedback to indicate their presence.
There are several different types of traffic
marking methods for the pavement surface. These include adhesive
strips, paints, and thermo-plastics. When in service, the
individual brick pavers continue to move independently of
each other to a slight degree. As such, the joints open and
close a small amount when a wheel passes over them. This movement
is often sufficient to cause cracking of the adhesive strip
and thermo-plastic markings. Although thinner paint markings
frequently have a shorter service life on other pavement materials,
they may be more cost effective on brick paved surfaces. Where
the visibility of traffic markings is not a legislated requirement,
inlaying contrasting colored pavers can provide the most durable
option.
Movement Joints [top]
Pavement materials expand and contract as a result
of temperature and moisture changes. Flexible pavement materials,
such as aggregate, asphalt concrete and cement treated base
materials, distribute this movement over the entire pavement
areas such that localized strains are very small. As a result
the pavers are unaffected by the underlying movement. Brick
pavers behave similarly, with any movement taken up in the
joints between pavers without putting stress on the brick
or edging. Expansion joints are therefore not typically required
in such flexible brick pavements. However, when a portland
cement concrete slab, used under the flexible brick paving
wearing surface, expands and contracts, the movement is concentrated
at the joints between the slabs. This movement will be reflected
into the overlying pavers, which can be detrimental to the
pavement. When the concrete contracts, it causes the overlying
joints to open. This results in a loss of interlock, settling
of the pavers and a loss of integrity. When the concrete expands
it causes the joints to close. This can impose large horizontal
pressure into the brick paver layer, possibly causing paver
movement that may result in chipping and spalling of the pavers,
and in extreme conditions heaving of the surface. It is therefore
necessary to continue expansion joints through the brick and
setting bed layer by incorporating edge restraints on either
side of the joint. This should be applied to both sand set
and bituminous set pavers.
Portland cement concrete slabs are also provided
with contraction joints to control cracking during curing.
Movement at these locations is less than at expansion joints,
and it is not normally necessary to reflect the joints into
the surfacing if the underlying contraction joints are at
less than 10 ft (3 m) centers. In order to distribute the
movement over a wider area it is beneficial to cover the control
joints with a strip of geotextiles under the sand bedding
course. This is not done under bituminous setting materials.
Design Examples
Examples are available in the Adobe® Acobat
version of this file. To
download the file click here.
Part II: Materials
Introduction [top]
The performance of any pavement is only as good
as the base, subbase and soil on which it is laid. Quality
materials for every layer in the pavement system are vitally
important to good performance. Materials should conform to
state or local department of transportation (DOT) specifications,
ASTM standards, or other applicable industry standards. Project
specifications typically require submission of qualifying
tests set by the standards.
Base and
Subbase Materials [top]
Some pavement systems contain only a base, while
others contain a base and a subbase. See Figure 1 for location
of layers. The quality or type of base and subbase materials
is usually dictated by the design requirements. The design
tables are based on various CBR values for the aggregate layers,
and compressive strength or Marshall stability for the cement
and asphalt treated layers.
Base materials may consist of unbound granular
materials, such as crushed aggregate; cement-treated or asphalt-treated
aggregates; or concrete and asphalt bases. Subbases are usually
composed of aggregate materials. Aggregate base and subbase
materials, including cement- and lime-stabilized materials,
are commonly specified in local state and municipal standards
for highway construction. All materials should conform to
state or local DOT specifications. Materials conforming to
ASTM or other industry standards can be used as alternates.
The choice and quality of base and subbase materials influences
the performance of the pavement. Typically, each layer material
can resist progressively higher stresses from the subgrade
upward to the wearing course.
Aggregates [top]
The National Stone Association has provided gradation
limits for base and subbase aggregate materials, see Table
12. This table is similar to requirements found in ASTM D
2940 Specification for Graded Aggregate Material for Bases
or Subbases for Highways or Airports.
Crushed, quarry processed aggregate is preferred
because of its ease of construction. The maximum size of aggregate
to be used in construction may depend on the size of the project
and the size of equipment being used. Proper gradation of
materials is required to achieve adequate compaction. Layers
consisting of single-size aggregate will not consolidate during
compaction and should not be used.
For flexible brick pavements subjected to pedestrian
and light vehicular traffic, aggregate graded to “3/4
minus”, similar to the gradations in Table 12, is usually
sufficient as a base material because it is easy to work with
and is readily available. Smaller graded aggregates or rounded
aggregates may not be sufficient to achieve interlock within
the aggregate layer and will not transfer loads properly.
Open graded (gap graded) aggregates can be used to promote
water drainage in areas subjected to frost heave to minimize
damage. Geotextiles may be needed to prevent intrusion of
smaller material into the open graded aggregates.
Asphalt Bases
New or existing asphalt bases can be used for
flexible brick pavements. Specification of asphalt concrete
should follow industry standards or local DOT requirements.
The adequacy of existing asphalt and the materials beneath
should be verified.
Concrete Bases [top]
New and existing concrete bases can be used for
flexible brick pavements. New concrete slabs should be specified,
with reinforcement as needed, and constructed according to
industry practice. Concrete bases should be properly cured
before installing the flexible brick paving. High early strength
cement may be used to reduce the time before the wearing surface
is placed. Existing concrete slabs should be checked for appropriate
strength and repaired or reinforced as necessary. A geotextile
can be used where there is a possibility of loss of sand through
cracks or holes in the existing slab. The adequacy of the
materials beneath the existing concrete slab should be verified.
Soil and
Base Stabilization [top]
Subgrade soils or granular material unsuitable
for use alone may be treated to produce a stronger layer.
The subgrade soil may be stabilized by adding portland cement
or lime, depending on the quality of the soil. Subbase and
base materials may be improved by adding portland cement,
lime, asphalt or pozzolanic materials. Modifying unsuitable
materials is considered when economically feasible or where
suitable untreated materials are in short supply, although
caution should be used in specifying treated soils. Their
use should be based on local availability and experience.
Subgrade soils or granular material unsuitable
for use alone may be treated to produce a stronger layer.
The subgrade soil may be stabilized by adding portland cement
or lime, depending on the quality of the soil. Subbase and
base materials may be improved by adding portland cement,
lime, asphalt or pozzolanic materials. Modifying unsuitable
materials is considered when economically feasible or where
suitable untreated materials are in short supply, although
caution should be used in specifying treated soils. Their
use should be based on local availability and experience.
Aggregate subbase materials, as well as cement-
and lime- stabilized materials, are commonly specified in
local state and municipal standards for highway construction.

Setting Beds
Sand Setting Bed [top]
Sand used as the setting bed should be a washed,
well-graded, sand with a maximum size of about 3/4 in. (4.8
mm). Sand conforming to ASTM C 33 Specification for Concrete
Aggregates is acceptable. Table 13 shows the gradation limitations
taken from ASTM C 33. In addition, the amount of material
passing the 75 µm (No. 200) sieve should be limited
to no more than 3 percent. The sand particles should be sub-angular.
For pavements subjected to heavy channelized traffic, experience
has shown that only naturally occurring, washed silica sand
with no silt content should be used. The gradation for the
silica sand in channelized traffic should be as shown in Table
14 and no more than 0.3% passing the 75 µm (No. 200)
sieve.
An excess of fine particles can increase the
moisture sensitivity of the bedding sand. Bedding sands with
high fines content can lead to rutting and movement forms
of distress. It is not only important to ensure that the fine
content is satisfactory on the selected bedding sand, but
also that it will not break down under heavy traffic. A degradation
test can be undertaken on the bedding sand to compare different
bedding sand options. The test involves rotating sand samples
with a charge of ball bearings, on a bottle roller for six
hours. The sand particles wear or break down in the process,
generating finer particles. The increase in fine particles
passing the No. 50, No.100 and No. 200 sieve sizes can be
compared with each other to select the best performing sand.
Mason’s sand, limestone screenings, or
stone dust should not be used as they do not compact uniformly,
are normally too soft, and some may cause efflorescence. Soft
materials, such as stone screenings, tend to break down over
time into smaller particles. Cement should not be added to
the sand because it makes removal and reuse of the pavers
difficult, adds to the expense of the system, and may cause
durability problems.
Bituminous Setting Bed [top]
The bituminous setting bed system can be used
as an alternative to a sand setting bed system. The sand bed
is replaced by an asphalt coated sand mixture that is bonded
to the underlying pavement layer with a tack coat. The brick
pavers are in turn bonded on to this bituminous setting bed
with a rubberized asphalt adhesive.

The most common material for the tack coat is
an SS-1 or SS-1h asphalt emulsion complying with ASTM D 977
Specification for Emulsified Asphalt. Typical application
rates are 0.05 to 0.15 gallons per square yard (0.23 to 0.68
liters per square meter) dependent on the surface texture
and porosity. Graded crushed aggregate base layers may require
up to twice this rate.

The asphalt cement for the bituminous setting
bed should be the same grade as that specified for the surface
course construction in the appropriate state department of
transportation or city highway specification. This may be
a viscosity grade conforming to ASTM D 3381 Specification
for Viscosity-Graded Asphalt Cement for Use in Pavement Construction
(AC-10 or AC-20, and AR-2000 or AR-4000 are the most common)
or a performance grade conforming to AASHTO MP 1 Specification
for Performance Graded Asphalt Binder (designated as PG grades
that are dependent on high and low temperatures in the area).
The type of asphalt cement will govern the mixing and rolling
temperatures. The fine aggregate for the bituminous setting
bed should be a natural or manufactured sand that complies
with ASTM D 1073 Specification for fine Aggregate for Asphaltic
Paving Mixtures, grading No. 2, or similar material used as
fine aggregate at the asphalt plant. All particles should
pass the No. 4 sieve. A typical gradation is shown in Table
15.

A local asphalt plant supplies the bituminous
setting bed material. Generally only small loads, up to 5
tons (4.5 metric tons), are required at one time so that the
work can be completed before the material cools and becomes
unworkable. It is manufactured by combining the dried fine
aggregate with hot asphalt in the asphalt plant. The approximate
proportions are 6-8% of asphalt cement with 94-92% of fine
aggregate or approximately 1 gallon of asphalt cement to 110
lbs of fine aggregate (1 liter to 13 kg). The exact proportions
should be verified before supplying material for the project.
The materials are mixed at a temperature of 300-325° F
(149-163° C).
The adhesive is generally a neoprene modified
asphalt product specifically developed for setting pavers.
It consists of a rubberized asphalt (typically 2% neoprene)
with inorganic fibers (typically 10% non-asbestos fibers).
However, other products including cold pour rubberized asphalt
crack filling compounds have also proven to be successful.
Jointing
Sand [top]
Jointing sand used between the brick pavers should
generally have smaller particles than the setting bed material
so that it completely fills the joints. The sand particles
should be sub-angular. Pavers without lugs and with tighter
dimensional tolerances may require finer jointing sand. Appropriate
materials must be used to avoid sand wash-out or sand being
sucked out by tires. Bedding sand (ASTM C 33) is recommended
for joint filling in heavy vehicular pavements. However, the
larger particles often will not enter the joints and should
be swept off the surface. The remaining sand particles require
significant encouragement to fully penetrate the joints. Success
has been obtained by passing the bedding sand through a No.
8 sieve. This can be done at the jobsite or by the sand supplier
before the material is delivered. Mason’s sand may be
used for lighter traffic conditions, and should be graded
to the limits in ASTM C 144 Aggregates for Masonry Mortar
shown in Table 16. The often rounded shape of the finer grade
mason’s sand makes it susceptible to removal from the
joints. Thus, the use of stabilizers should be seriously considered.
Other successful sands have been specially graded, dried and
bagged for joint filling. They are frequently available from
some paver manufacturers. Limestone screenings or stone dust
should not be used for the reasons listed under Setting Beds.

For bituminous setting bed systems it is necessary
to provide stabilized joint sand as the joint sand is not
as well packed into the joints. Without a stabilizer, creep
can be excessive and joint sand erosion is likely. Mixtures
of portland cement and sand have been used with varying success,
but are not recommended. If such a mixture is used it should
consist of 1 part of portland cement and 6 parts of sand.
The materials are mixed dry before filling the joints, and
are brushed over the surface. The surface is fogged so that
water penetrates the joints and hydrates the cement. Staining
or a resulting rigid system is undesirable results of this
practice.
Liquid polymer sealants are proving to be more
successful than the sand cement mix. They can also be used
for areas subjected to heavy flows of water. These products
are a water repellent, applied to bind jointing sand particles
together. It is typically sprayed and squeegeed over the surface
so that it soaks into the joint sand and only a thin film
remains.
Dry mix stabilizers are mixed with dry jointing
sand and swept into the joints. The binding mechanism is activated
by applied water. In order to achieve satisfactory penetration
and binding of the sand, it is inappropriate to use the ASTM
C 144 manufactured sand when liquid polymer sealants are applied.
This sand has a high percentage of very fine particles which
prevent the penetration of the stabilizer to a satisfactory
extent. The stabilizers should bind the sand in the top 1/2
in. (12 mm) of the joint.

Brick Pavers [top]
Brick pavers should conform to ASTM C 902 Specification
for Pedestrian and Light Traffic Paving Brick or ASTM C 1272
Specification for Heavy Vehicular Paving Brick. The paving
pavers are classified by the type of traffic the pavers are
subjected to during use.
Pavers covered by ASTM C 902 are intended to
support pedestrian and light vehicular traffic with low volumes
of traffic. The pavers can be used in applications such as
residential patios and driveways, sidewalks, plazas, and commercial
driveways. Pavers covered by ASTM C 1272 are intended to support
high volumes of heavy vehicles. The heavy duty pavers can
be used in applications such as roads, streets, and crosswalks.
Heavy vehicular traffic is defined as high volumes of heavy
vehicles representing trucks or combination vehicles that
have 3 or more loaded axles. A possible measure of high volume
is over 25 ESALs per day or 200,000 ESALs over the pavement
life. Table 17 shows the traffic type and applications for
brick pavers.
Minimum Thickness [top]
Brick pavers set in a sand setting bed with sand
between the pavers used in a heavy vehicular pavement require
a minimum thickness of 2-5/8 in. (67 mm) to achieve interlock.
This thickness is exclusive of any chamfers. Thinner pavers
will not provide interlock and may move in place, allowing
cracking of the pavers. The same thicknesses apply to pavers
on bituminous setting beds.
Durability [top]
The durability of brick pavers is predicted by
properties such as compressive strength, absorption and saturation
coefficient. The saturation coefficient, also referred to
as the C/B ratio, is the ratio of 24 hour cold water absorption
to the 5 hour boiling water absorption. ASTM C 1272 requires
the brick to meet a minimum compressive strength and a maximum
cold water absorption. ASTM C 902 pavers must meet a minimum
compressive strength, a maximum cold water absorption, and
a maximum saturation coefficient. Table 18 shows the physical
property requirements for the different classes of paving
brick. Paving brick subjected to freezing temperatures should
equal or exceed the physical property requirements for ASTM
C 1272, Type R or F, or ASTM C 902, Class SX.
Because raw materials and production methods
for brick vary throughout the country, it is difficult to
use only the physical property requirements to classify all
brick. Therefore, there are alternates which permit the use
of those brick which perform satisfactorily in service but
do not meet the physical requirements listed in Table 18.
Using the alternates in ASTM specifications permits the use
of brick that are known to perform well in their intended
application. It does not signify that the brick are of a lower
quality.
Flexural Strength [top]
It is unlikely that a brick paver will ever fail
in compression (crushing) while in service. Instead, the critical
property is the flexural strength. A point load, such as a
tire, transmits a force to the paver that is supported beneath
by a uniform resisting load. The ability of a brick paver
to resist a point load is measured by either the modulus of
rupture or the breaking load. Each is evaluated according
to ASTM C 67 Test Methods of Sampling and Testing Brick and
Structural Clay Tile AASHTO T32. In these tests an individual
paver is supported near its ends and a downward force applied
midway between the two supports. ASTM C 1272 establishes a
minimum breaking load value shown in Table 18. ASTM C 902
does not have requirements for flexural strength.
Abrasion Resistance
Paving brick are exposed to the abrasive effect
of pedestrian and vehicular traffic. Of these two types of
traffic, pedestrian traffic can cause the most wear of the
pavement surface. Areas attracting concentrations of pedestrian
traffic, such as doorways, gates, and even automatic teller
machines, deserve special attention. The high volume and impact
force of high-heeled shoes cause the highest degree of abrasion.
Tires on roadways do not have such a drastic effect, unless
studded tires are permitted. Brick roads will polish with
repeated tire traffic which results in a slightly lower skid
resistance value.
The abrasion resistance of brick pavers is determined
in one of two ways: 1) an abrasion index is calculated by
dividing the cold water absorption by the compressive strength
and then multiplying by 100, or 2) by determining the volume
abrasion loss in accordance with ASTM C 418 Test Method for
Abrasion Resistance of Concrete by Sandblasting. The abrasion
requirements for paving brick are listed in Table 19.
The abrasion index is an expedient measure since compressive
strength and absorption tests must be calculated for durability
purposes. The abrasion index has correlated well with in-field
performance.
The volume abrasion loss is determined by submitting
a paver to the sandblasting test for a duration of two minutes.
The flow rate and grading limits of the sand differ slightly
from ASTM C 418. The volume loss is determined by filling
the abraded depression with modeling clay, then calculating
the volume lost during sandblasting.

Slip and Skid Resistance [top]
The slip resistance of a paving surface is related
to pedestrian traffic, while skid resistance is related to
vehicular traffic. The slip and skid resistance are measures
of the slipperiness of a surface. A surface with a high slip
or skid resistance is relatively safe, while a low value may
indicate a hazardous surface.
Slip resistance is adversely affected by water
on the surface of the pavement. It is the surprise of walking
from a slip resistant surface onto a wet or nonslip resistant
surface that causes many falls. Since the slip resistance
relies on the microtexture of the paving brick, a brick with
a rougher wire cut surface will have a higher slip resistance
value.

Skid resistance measures the potential of vehicles
skidding on the roadway surface. For the relatively slow speeds
expected on flexible brick pavements, the skid resistance
depends upon the microtexture of the paver surface. Joints
between the pavers and chamfered edges also have a positive
effect on the overall skid resistance. A pendulum friction
tester is used to measure skid resistance. The pendulum tester,
ASTM E 303 Method for Measuring Surface Frictional Properties
Using the British Pendulum Tester, measures the wet skid resistance
value of unused individual pavers. Typical values for new
brick pavers from the British Pendulum Test range from 50
for smooth pavers to over 80 for wirecut surfaces. Other tests,
such as the fixed trailer, allow the testing of larger sections
of pavements that take into account the positive aspect of
joints.

Over time, the skid resistance of all paving
surfaces decreases because of the polishing effect of the
traffic. The skid resistance value for most brick is initially
very high and decreases while in use, approaching an equilibrium
condition several months after placement. The skid resistance
values are also affected by seasonal factors. The British
Pendulum Tester can also measure the Polished Paver Value
(PPV) after the paver has been in service.
Dimensions [top]
The size and the associated dimensional tolerances
of paving brick are more important in flexible brick pavements
than in other brick paving applications. Consistent dimensional
tolerances allow consistent joint sizes. This in turn ensures
interlock and may reduce chippage. Commonly available sizes
of pavers for flexible pavements are listed in Table 20. Rectangular
pavers may have a small chamfer or rounded edges. When these
are present it is recommended that they not exceed 3/16 in
(4.8 mm) in depth or width. The minimum height of the paver
necessary for interlock does not include the height of any
chamfer. Specially-shaped pavers are available from some manufacturers
lending a decorative effect to the pavement. The shape, other
than the ratio of maximum length to thickness, has no measurable
effect on the interlock between the pavers or on the strength
of the pavement. Pavers should be dimensioned so that the
ratio of maximum length to thickness is less than 3 to 1.
Some pavers also are made with lugs or spacers.
These lugs, usually 1/8 in. (3 mm), space the pavers apart
and provide a uniform gap for jointing sand. The lugs also
keep the paver edges from touching during compaction and in
service. This may reduce the amount of chippage on the paver.
Lugs are usually necessary when the pavers are subjected to
heavy vehicular traffic. When lugs are on only one side or
one end of the paver, they are included when measuring the
length or width. This approximates the dimensions between
the centers of the joints. When lugs are included on both
sides and both ends of the paver, the lugs share the space
between the pavers. Thus, only one lug is included when measuring
the length or width of the paver.
The dimensional tolerances for pavers are shown
in Table 21. For flexible pavements subjected to vehicular
traffic, ASTM C 1272, Type F or ASTM C 902 Application PX
is recommended. Brick with larger dimensional tolerances will
be difficult to install, especially with herringbone and basketweave
patterns, and may not provide interlock.
Other
Materials [top]
Surface Coatings
Colorless coatings (i.e. water repellents) are
generally not recommended on exterior brick pavements. The
wrong type of coating may not permit vapor transmission (evaporation)
and may trap water within a paver. This may lead to damage
due to freeze/thaw or spalling of the face due to build up
of crystalline deposits of soluble salts or ice beneath the
coating. Non-penetrating type coatings will wear off quickly
in high traffic areas.
However, coatings that prevent erosion of the
jointing sand may be beneficial. In that case, the coating
should be of a type that has a high vapor transmission rate,
and will not affect the slip/skid resistance of the paver.
The stabilizer should be water based.
Geotextiles
Geotextile fabric materials can be used to separate
layers of materials in the paving system. Geotextiles can
also be used as a filter material in many drainage applications.
Subgrade soil can be prevented from migrating into the base
or subbase by use of a geotextile. Other uses of geotextiles
range from providing erosion control to being used to reinforce
subgrade beneath the pavement by adding strength to the system.
Geotextile manufacturers should be consulted to determine
applicability of geotextiles in flexible brick paving applications.
The recommended minimum apparent opening size of the geotextile
should be No. 70 (0.2 mm). The geotextile fabric may be either
woven or nonwoven, and should be placed so that the material
extends up the side of the excavated area a sufficient distance
to cover the base material. They should overlap approximately
24 to 36 in. (610 to 914 mm) to maintain strength. Only woven
geotextiles should be used directly under the bedding sand,
as this location is highly abrasive, and can separate the
fibers on non-woven materials
Edge Restraints [top]
Edge restraints are mandatory in flexible brick
pavements. Edge restraints hold the pavers together and provide
for interlock of the wearing surface. Many different types
of edge restraint materials exist, including brick, rigid
plastic, wood, steel, aluminum, or concrete. The type of application
determines which material to use. Any of the materials listed
can be used in pedestrian applications. Only concrete, brick
placed in concrete, some varieties of rigid plastic, or steel
edgings should be used in areas subjected to vehicular traffic.
In heavy vehicular applications, only cast-in-place concrete
should be used. Flexible pavement materials, such as brick
set in sand, loose aggregates, or asphalt, are not suitable
as edge restraints.
Part III: Construction [top]
Introduction
The in-service performance of the pavement depends
on the preparation and installation of the underlying materials.
If the materials are not placed and compacted properly, then
the entire brick pavement system may not perform as intended.
Properly sized joints between pavers, completely filled with
jointing sand, are essential to complete interlock and for
long term performance.
Subgrade [top]
The subgrade is excavated, if necessary, to achieve
the required finished level. Any unsuitable material, such
as organic material, large rocks, etc., should be removed
from the subgrade and replaced with suitable backfill. The
subgrade should be drained and protected against flooding
and ground water by sub-soil drainage. The installation of
pipes and sub-soil drainage should be completed before initiating
the base or subbase construction. The width of the subgrade
should be sufficient to extend to the back edge of the proposed
edge restraint or abut existing structures.
To achieve the best performance from the subgrade
it is necessary to scarify the top surface, condition it to
the proper moisture content, and then to recompact it to established
relative densities. The moisture content of the soil must
be within allowable limits of the optimum moisture content
and be carefully monitored to achieve maximum compaction.
The subgrade soil should be compacted to at least 95% maximum
density if they are granular and to at lease 90% maximum density
if they are cohesive. The method of compaction and compaction
equipment may vary due to soil type and size of area being
compacted. Figure 9 is a general guide to the appropriate
choice of compaction equipment. Subgrade preparation is commonly
specified in local state and municipal standards for highway
construction. It is also likely that the geotechnical report
will provide recommendations on minimum compaction standards.
Various tests are used to determine the proper
compaction and density of the soil. Laboratory compaction
tests to determine proper placement requirements include:
Standard Proctor Test, ASTMD 698 Methods for
Laboratory Compaction Characteristics of Soil Using Standard
Effort (12,400 ft-lb/ft3 (600 kN-m/m3)) or AASHTO T9 Test
Methods for Moisture-Density Relations of Soils and Soil-Aggregate
Mixtures Using 5.5 lb. (2.5 kg) Rammer and 12 in. (305 mm)
Drop; and
Modified Proctor Test, ASTM D 1557 Test Method
for Laboratory Compaction Characteristics of Soil Using Modified
Effort (56,00 ft-lb/ft3(2,700 kN-m/m3)) or AASHTO T180 Test
Methods for Moisture-Density Relations of Soils and Soil-Aggregate
Mixtures Using 10 lb. (4.5 kg) Rammer and 18 in. (457 mm)
Drop.
The latter of these tests is normally used to
test materials that support heavier loads for higher shear
strength.
Field tests which determine soil density provide
a method to check for conformance to job specifications. Three
field tests are often used:
Sand Cone Test, ASTMD 1556 (AASHTO T191) Test
Method for Density and Unit Weight of Soil in Place by the
Sand Cone Method.
Water Balloon Test, ASTM D 2167 (AASHTO T205)
Test Method for Density and Unit Weight of Soil in Place by
the Rubber Balloon Method; and
ASTM D 2922 (AASHTO T238) Test Methods for Density
of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow
Depth).
It is important to remember that the maximum
density varies between samples, and so proper soil identification
is required to establish the appropriate target density for
each location.
Because brick paving is frequently used as hard
landscaping adjacent to major building projects, it is often
the case that designers are not familiar with highway testing
and construction procedures. Therefore, great care must be
taken in evaluating and testing the subgrade. For best results
then, follow the procedures outlined in this Guide along with
the advice of a pavement design professional.
Subbase [top]
This Guide considers various types of subbase
material as set out in Table 7 and the associated text. These
include graded aggregate, cement- and lime- stabilized soils.
Basic assumptions on the types of materials are in the table.
Subbase courses should be designed following Part I of this
Guide, or guidelines and specifications of local authorities.
Geotextile fabric may be used to separate the
subgrade soil from an aggregate subbase, especially in soils
subject to moisture levels near or at saturation. The geotextile
will prevent intrusion of the subgrade soil into the bottom
of the aggregate subbase or vice versa. They must be placed
without wrinkles and lapped at their edges.
The aggregate subbase course materials should
be spread and compacted in layers. In-place mixing and compaction
of the stabilized materials can be carried out, or mixing
can be undertaken remotely and the mixture spread and compacted
in layers. The thickness of these layers must be consistent
with the capabilities of the compaction equipment. All subbase
materials should be compacted to a minimum of at least 95
percent of maximum density. The subbase should also extend
at least one layer thickness past the edge of the overlying
layer to enable adequate compaction at the edges of the pavement.
Typically, the thickness of each layer is approximately 3
to 4 in. (76 to 102 mm), but can increase to double these
thicknesses if appropriately heavy compaction equipment is
used.

Compaction should be completed as soon as possible
after the material has been mixed and spread. The profiles
should be such that water is channeled towards drainage facilities.
Base [top]
The design tables in this Guide provide options
for various types of base course material. These include graded
aggregate bases, cement-treated bases, and asphalt-treated
bases. Thickness of portland cement concrete slabs on an aggregate
subbase is also considered. Details can be found in Table
7 and the associated text. Base courses should be designed
following Part I of this Guide, or guidelines and specifications
of local authorities.
Geotextile fabric may be used to separate the
subgrade soil from the compacted base, especially in soils
subject to moisture levels near or at saturation. The geotextile
will prevent intrusion of the subgrade soil into the bottom
of the aggregate base or vice versa. They must be placed without
wrinkles and lapped at their edges.
The base course materials should be spread and
compacted in layers. The thickness of these layers must be
consistent with the capabilities of the compaction equipment.
See Figures 10 and 11. All base materials should be compacted
to a minimum of 95 percent maximum density. The base should
also extend at least 6 in. (150 mm) past the edge restraint
if spikes are used to hold the restraint in place. Typically,
the thickness of each layer is approximately 3 to 4 in. (76
to 102 mm). The surface of the base should be close-knit to
prevent setting bed material from filtering downwards through
the base. It must be of good quality to avoid failure due
to high stress concentrations immediately under the wearing
surface.
Compaction should be completed as soon as possible
after the material has been spread. It is essential that the
intended surface profile of the base be formed so that the
pavers can be placed on a uniform thickness of bedding sand.
Sand Setting
Bed [top]
The sand setting bed material is spread over
the base in a uniform thickness. The setting bed is not meant
to, and should not, be used to fill in low spots or bring
the pavement to the correct grade. The thickness of the setting
bed should be 1 in. (25 mm) thick with a tolerance of plus
or minus 3/16 in. (5 mm) Setting bed thicknesses that are
excessive could lead to shifting of the setting bed material,
causing loss of strength.
The sand is typically spread over the base between
1 in. (25 mm) diameter screed rails. These are set to a profile
to provide sufficient depth in the uncompacted bedding layer,
to account for the reduction from compaction. Screed rails
are typically placed 8 to 12 ft. (2.4 to 3.7 m) apart, and
at closer centers when a changing grade is required. There
are several specialized screeding systems that enable more
rapid installation and result in less foot traffic on the
sand. On some large projects, asphalt paving machines have
been used to spread the sand.
The setting bed sand should not be spread too
far in front of the laying face of the pavers to prevent disturbance.
The sand should be screeded without compaction to a level
slightly higher than the final thickness of the layer. See
Figure 12. The sand should be disturbed as little as possible
since the final pavement surface will reflect any variation.
The voids left by the screed rails should be filled from the
paver laying face as work progresses. The common practice
of filling from the screeding side can leave localized areas
of over compacted sand, which results in subsequent high spots.
If the sand is disturbed, the area should be rescreeded. Prepared
areas should not be left overnight, unless they are properly
protected from disturbance and moisture. The moisture content
of the setting bed sand should be as uniform as possible,
and the material should be moist without being saturated.
Water should not be added to screeded sand except as a very
light misting. Stockpiled material should be kept covered.
The screeded bedding sand is vulnerable to environmental
disturbance from wind or rain. Care needs to be taken so that
water cannot drain back into the bedding sand when it is uncovered
or covered with pavers but not vibrated.
Bituminous Setting
Bed [top]
The first step in constructing this system is
to apply a tack coat over the base layer to achieve a level
of bonding and moisture protection. The tack coat will generally
be supplied to the site in drums or pails due to the limited
area at any application time. The air and substrate temperature
should be above 50 degrees F (10 C). The material should be at a temperature
of about 80 degrees F (27 C) or above when applied. A continuous,
uniform coat should be applied by spraying, squeegeeing or
brushing the material. Typical application rates are 0.05
to 0.15 gallons per square yard (0.19 to 0.57 liters per square
meter), depending on surface texture and porosity. Work should
not be carried out in rainy conditions. The tack coat must
cure for 1/2 to 1 hour (until it turns black and is dry to
the touch) before applying the bituminous setting bed.
A local asphalt plant supplies the bituminous
setting bed material. Generally only small loads, up to 5
tons (4.5 Mg), are required at one time so that the work can
be completed before the material cools and becomes unworkable.
The materials are mixed at a temperature of 300 to 325 degrees F (149
to 163 C). The mixed material should be delivered to the site
in an appropriate covered truck. The truck bed should be steel
that is clean and a lubricant should be used to help with
discharge.
Steel screed rails, typically 12 ft. (3.7 m)
long, are set up on timber packs to achieve a uniform profile.
These are typically at 10 to 12 ft (3 to 3.7 m) centers, oriented
along the profile of the street. When establishing the profile,
it is important to allow for the likely compaction of the
setting bed. The hot material is spread over the surface of
the tack coat and screeded off to a nominal thickness of 3/4
in. (19 mm). Care should be taken to ensure that release agents
applied to the screed rails and tools do not cause damage
to the bituminous setting bed. The screeded panels are advanced
down the street as each screed rail length is completed. To
minimize foot traffic on the screeded material, alternate
panels are constructed so that the screed rails and timber
packs can be removed and the infill panel screeded using the
edges of the two outside panels. The infilling of narrow slots
where screed rails have been removed should be minimized,
as this can result in a variable density and differential
compaction. Screeding should be undertaken while the material
is still hot. Particles of colder material will drag under
the screed rule and result in a rough surface. As the layer
is thin it will cool quickly. Once the asphalt sand mixture
has cooled to a suitable temperature it is rolled to provide
a smooth, uniform surface. A walk-behind or small ride-on
steel drum roller, with a weight of 200 to 300 lbs per ft
(300 to 450 kg per m) width of drum, should be used. On small
projects and in confined locations, a vibratory plate compactor
may be used.
There are two different degrees of compacting
the bituminous setting bed. In one, the bituminous setting
bed is laid and lightly compacted with the roller. This results
in a setting bed with an open texture and high void content.
In the second system, the bituminous setting bed is more thoroughly
compacted during the rolling process. This results in a more
closed surface with less texture.
Paver Installation [top]
General
Work may start from an exact edge or from the
centerline of the pavement. The pavers should not be forced
together, as this can result in excessively tight joints,
which may cause the pavers to chip during installation or
compaction. The pavers should be laid in the desired bond
pattern, with a joint width between 1/16 in. (1.6 mm) and
1/8 in. (3 mm) on all sides. Pavers that butt directly against
the adjacent paver result in chipping as the system flexes.
Pavers with lugs provide the correct gap when they are placed
in contact with each other.
String lines or chalk lines may be used to keep
the pattern straight. Straight and true bond lines are necessary
in areas subjected to heavy vehicular traffic to provide a
uniform distribution of horizontal loads. The spacing of the
string lines should be based on the contractor's experience,
size of the project and speed of laying. It is inadvisable
to open joints above 1/8 in. (3 mm) to avoid cutting at an
edge. The wider joints are likely to lead to greater creep
and a reduction in structural integrity.

Whole pavers should be laid first, followed by
cut pavers. After the area is laid with whole pavers, it is
easy to fill in the spaces with pavers cut to size. All pavers
should be cut with a masonry saw to produce an accurate, clean
cut. The blade should have a soft bond matrix and a high diamond
concentration in order to cut clay pavers effectively. A trial
area may be laid out in advance of work to determine paver
positions to minimize the amount of cutting and maintain cut
pieces of sufficient size. A rule of thumb is to have the
minimum face dimension of the cut piece not less than the
paver thickness. It is common practice to run one or two rows
of pavers laid in stack bond (sailor course) along edge restraints.
This facilitates subsequent cutting of pavers and ensures
that the cut is between similar materials.

A herringbone pattern laid at 45 or 90 degrees to the
edge of the pavement should be used for vehicular applications.
A 45 degree herringbone may be started along an edge and continue
parallel to that edge. See Figure 13. A 90 degree herringbone should
be started, if possible, at an exact corner or the centerline
of the area to be paved. Otherwise, a "pyramid"
of pavers should be advanced over the area along a line, as
in Figure 14. If a running bond pattern is used, the pavers
should be laid so that their long dimension is perpendicular
to the flow of traffic. In all cases, the bond pattern should
be checked periodically to ensure proper alignment. Slight
adjustments can be made in the thickness of the joint, since
it is far easier to replace a row or two of pavers than to
reconstruct an entire area.
Pavers on Sand Setting Bed [top]
The installer works off of the pavers already
in place. Felt or other geotextiles should not be placed directly
beneath the brick pavers. Felt does not allow interlock, since
the setting bed is not allowed to integrate with the jointing
sand between the pavers during compaction. After the pavers
have been placed on the sand setting bed, the brick pavement
is vibrated by a mechanical plate vibrator/compactor. The
first pass is done without jointing sand spread on the surface,
as shown in Figure 15. Prior to subsequent passes of the compactor,
jointing sand is spread across the surface before compaction,
as shown in Figure 16. The jointing sand should be dry and
spread on the pavement until the joints appear full. If movement
of the pavers occurs as a result of wide joints adopted when
the bricks do not have spacers, a light distribution of bedding
sand over the surface before vibration can be beneficial.
If chipping of the pavers occurs, laying geotextiles material
on the surface before vibration can be beneficial. Obviously
the initial vibration and placement of the jointing sand should
be accomplished as soon after placing the pavers as possible
and before any traffic is permitted on the paving.
A plate compactor with a high frequency/low amplitude
plate, equipped with a rubber mat or a rubber-roller mechanical
vibrator, is used. Use of a steel drum roller is likely to
cause some cracking of the bricks. If it is used in vibration
mode, significant damage can occur. The plate area should
not be less than 2 ft2 (0.19 m2) and produce 3,000 to 5,000
lbs. (13.3 to 22.3 kN) of centrifugal force. Compaction should
not occur within 6 ft (2 m) of any unrestrained edge.
Pavers on Bituminous Setting Bed [top]
The pavers are set on an adhesive spread on the
bituminous setting bed. When the setting bed is lightly compacted,
the adhesive drains down into the surface texture of the setting
bed. With the light compaction the pavers are typically loose
at first so they can be aligned. When the pavement surface
carries traffic, the pavers compress the lightly compacted
setting bed and squeeze the adhesive back to the interface
between the setting bed and the pavers. This achieves a good
bond and full coverage of the bottom of the paver. It is good
practice to roll the surface of the completed paving with
a heavy rubber tire roller. This will enhance the compaction
of the bituminous setting bed if the pavement is to be used
by heavy vehicles, reducing the likelihood that rutting will
develop in the wheel paths.
When the setting bed is highly compacted, the
adhesive does not penetrate into the setting bed and the quantity
of adhesive can be better controlled. Troweling is typically
used to spread it. The pavers are then set close to their
final position, as they become difficult to move when the
adhesive hardens.
The adhesive can be cold applied, but should
be above 70 degrees F (21 C) for best results. It is applied at a
coverage rate of 30 to 50 sq ft per gal (0.84 to 1.2 sq m
per liter), by brush, squeegee or trowel, depending on its
viscosity. The adhesive should be spread at least two hours
before setting the pavers.
The brick pavers are placed by hand onto the
adhesive. The installer works off of the pavers already installed.
They are placed with joint widths of 0 to 1/16 in. (1.6 mm)
to the correct laying pattern, and aligned as soon as possible
to form straight lines. Wider joints should be discouraged
and the pavers should be placed as close together as possible
while maintaining the alignment. When the pavers have lugs,
they may be placed in contact with each other for best results
and to minimize creep.
Traffic should not be permitted on the paving
until the joints are filled with jointing sand that is stabilized.
The preferred method is to use dry sand and a stabilizer.
Dry joint sand is brushed into the joints in the same manner
as for sand set systems. No vibration is used. When the joints
are full, the sand is swept off so that it is level with the
bottom of the chamfers or the top of the pavers. If a dry
stabilizer is used, it is mixed with the dry sand prior to
application. The dry stabilizer is activated with applied
water to bind the sand particles. A liquid joint sand stabilizer
that binds the sand particles together, if used, is applied
after the dry sand is brushed into the joints and the excess
swept off. It is sprayed and squeegeed over the surface so
that it soaks into the joint sand and only a thin film remains
on the surface of the pavers. It is important that the stabilizer
is water based as solvents can harm the adhesive and setting
bed materials. It is possible to wet the surface of the pavers
or allow time for the sand to settle to encourage complete
filling of the joints. However, the moisture should be allowed
to dissipate prior to applying liquid stabilizer.
An alternative, and not recommended process,
is mixing cement with dry joint sand and brushing it into
the joints. No vibration is used. When the joints are completely
filled, the surface of the pavers is lightly misted so that
the water penetrates the joints and hydrates the cement. It
is possible that some settlement of the joint filling material
will occur so that a second treatment may be required. Care
must be taken to ensure that no cement is left on the pavement
surface as stains may result. This is particularly difficult
if the pavers have a rough surface texture or are engraved.
Tolerances [top]
The final surface elevation should be left slightly
above adjacent pavement to allow for secondary compaction
of the bedding layer under traffic. It is typical for an additional
1/8 in. (3 mm) of compaction to occur, but local experience
should govern. The maximum variation in level should be within
±3/16 in. in 10 ft (± 5 mm in 3 m). Pavers adjacent
to drainage inlets and channels should be left slightly higher,
but not more than 3/MR in. (5 mm) above it. The edges of any
two adjacent pavers should not differ more than 1/8 in. (3
mm) if the pavers have chamfers, or 1/16 in. (1.6 mm) if they
have square edges. Paver to paver tolerances are measured
either chamfer to chamfer or top edge to top edge. The bond
line to which the paver pattern is laid also has dimensional
tolerances. These should be within ± 1/2 in. in 50
ft (± 10 mm in 15 m).
In
Service Considerations [top]
Surface Coatings
Colorless coatings, i.e. water repellents, are
generally not recommended on exterior brick pavements. See
the discussion in Part II: Materials. If surface coatings
are to be applied, the manufacturer's instructions for application
should be followed.
Repairs
At some time during the life of a flexible brick
pavement, repairs or utility work beneath the pavement may
require the removal and replacement of pavers from the working
area. When starting repairs, a single brick should be removed,
preferably with a purpose-made tool. It may be necessary to
break a few pavers to start the removal. Adjacent pavers are
then be removed and stacked nearby to be used again if not
damaged. The pavers should be cleaned of adhering sand by
brushing. Cleaning of asphaltic material is usually difficult,
and it may be necessary to remove pavers set on bituminous
setting beds from the site for cleaning with a solvent. Temporary
edge restraints should be placed at the perimeter of the removal
area.
Excavation of trenches should follow established
procedures. Proper compaction of the returned fill material
is very important. If the area is too small for proper compaction,
stabilized materials, such as concrete, should be used. The
compacted fill should be brought up to the proper level. One
or two feet (0.3 to 0.7 m) of pavers around the perimeter
of the excavated area should be removed so that accurate levels
can be established from undisturbed work. At all times, vehicular
traffic should be kept at least 6 ft (2 m) away from the work
edges.
Setting bed material should be screeded to the
proper grade. The setting bed should be compacted and a thin
layer of sand screeded on top. Temporary edge restraints are
removed and the pavers are then laid in the correct bond pattern.
Some creep of the pavement may have occurred during repairs;
therefore, some pavers may have to be saw cut to fit. Jointing
sand should be spread over the top of the pavers and the system
vibrated to the finished level with a plate compactor. Two
or three passes may be necessary to fill the joints. Dependent
upon the type of backfill used in the excavation, it may be
appropriate to set the pavers high of the final surface so
as to accommodate any consolidation. Providing a slight arch
to the profile will help in maintaining a good fit.
Maintenance [top]
Although brick paving surfaces are very durable,
some routine maintenance may be necessary.
Efflorescence
Efflorescence, a white powdery substance produced
by soluble salts, may be unavoidable on a paving surface.
Deicers used on adjacent areas may be deposited onto the brick
pavement, soluble salts may be present within paving system
components, or salts may migrate from adjacent soils. Therefore,
proper drainage and maintenance are especially critical to
reduce the amount of efflorescence. If efflorescence does
appear on the paving surface, natural weathering or traffic
will usually eliminate it. Efflorescence should not be removed
from the surface with acids. There are proprietary efflorescence
removers available.
Snow Removal
Snow removal from brick pavements should not
present any particular problem. It can be removed by plowing,
blowing or brushing away the snow. When using plows or shovels
there are precautionary measures that can be taken to preserve
the surface character of the brick. Metal blades should be
rubber or urethane tipped or mounted on small rollers. The
blade edge should be adjusted to a clearance height suitable
for the pavement surface. When hand shoveling, shovel at an
angle to the paver edge to avoid catching it. Avoid the use
of any chemicals containing rock salt (calcium chloride) to
aid in melting ice. Use of these materials may cause efflorescence.
Calcium magnesium acetate is recommended for snow and ice
removal. Urea is used to melt ice at many airports without
causing efflorescence, but it is not effective below 20 degrees F
(-7 C). Otherwise, remove snow before it can be compacted
or turn to ice. To render icy surfaces passable, use clean
sand or ashes on the icy areas.
Closing [top]
Brick has been used as a paving material for
centuries, however, the design and construction of an interlocking
flexible brick pavement for heavy vehicular applications is
a fairly new concept. This Guide provides designers with information
on how to design, construct and specify a properly performing
flexible brick pavement. The materials and construction procedures
recommended in this Guide are similar to those used for other
pavements.
References [top]
- American Association of State Highway
and Transportation Officials, Guide for Design of Pavement
Structures, Washington, D.C., 1993.
- Brick Development Association, BDA
Design Note 9, Flexible Paving With Clay Pavers, United
Kingdom, Oct. 1988.
- Brick Industry Association, Flexible
Brick Pavements: Heavy Vehicular Pavements, Design and Installation
Guide, Reston, Virginia, 1991.
- Clay Brick and Paver Institute, Paver
Note One, Specifying and Laying Clay Pavers, Australia,
Aug. 1989.
- Clifford, J.M., Segmental Block Paving
in Southern Africa - A Review and Structural Design Guide,
National Institute for Transport and Road Research, Republic
of South Africa, Sept. 1986.
- Knapton, J. and Barber, S.D., UK
Research into Concrete Block Pavement Design, 1st Concrete
Block Paving Conference, Newcastle-upon-Tyne, United Kingdom,
1982.
- Knapton, J. and Mavin, K.C., Design
Manual 1, Clay Segmental Pavements, Clay Brick and Paver
Institute, Australia, Jan. 1989.
- National Stone Association, Flexible
Pavement Design Guide for Roads and Streets, Jan. 1985.
- Pavement Consultancy Services, Structural
Design of Roads and Streets using Concrete Block Pavements,
National Concrete Masonry Association, Herndon, VA, Jan.
1989.
- The Total Concept, Blockleys, plc,
United Kingdom, 1988.
- Understanding Soil Compaction, J.I.
Case Co., Racine, WI, 1988.
- Walsh, I.P., A Comparative Field
Study of the Performance of Brick Pavers, Chemistry and
Industry, Nov. 1985.
Appendix [top]
A complete appendix is included in the Adobeª
Acrobatš version of this document. Click
here to download this document in PDF format.
Brick
Industry Association
11490 Commerce Park Dr.
Reston, Virginia 20191
www.brickinfo.org
[top] |